Painting a 4-room HDB flat takes approximately 2 days, depending on specific conditions.
This is based on a 2-person painting and 2 coats of paint on the wall and ceiling. The paint will take about 2 to 4 hours to dry before applying the second coat. To quicken the process, turn on the fan and open the windows to allow for air circulation.
4 Examples that will delay the painting duration for 4-room HDB
1) Oil sealer: An additional day is needed if you are using oil sealer to paint the entire 4-room HDB.
2) Spalling Concrete: the falling apart and breakdown of concrete wall or ceiling surfaces, where lumps or peeling of concrete break off, often reveal the steel reinforcement beneath. If the area is small, you can repair it. If the spalling concrete is big, engage a contractor or us to repair.
3) Spalling paint or peeling paint or flaking paint: It means the separation of paint from a surface, often due to unrevealed issues like moisture, poor adhesion, temperature fluctuations, improper surface preparation, poor quality paint, expired paint, surface contamination, movement of substrate, or structural problems.
4) A lot of furniture and/or items in the HDB unit: We need space to paint, so we’ll move the furniture to make room. We charge additional fees when there is a lot of furniture to move, and items to pack or dispose of.
2 Examples that will Quicken the Painting Duration of 4-Room HDB
1) Choose a water-based sealer: If you want to quicken the process and still use a sealer, consider using a water-based sealer instead, as it dries faster and has low odour (low VOC).
2) Pack your home, before we start painting: This will defiantly save time and money for you.
Summing It Up for Painting 4 Room HDB Duration
Hopefully this information didn’t only educate you, but help you to decide to DIY painting or get professional help.
If you have any questions regarding painting your 4-room HDB flat, do look up our More FAQs for answers.
Or if you decide to get a pro HDB painters, why not try us out?
FAQs
How long does it take to paint a 4 wall room?
It will take about a day to paint a room of 4 walls. It will take less than a day if the room is empty.
It takes about 2 to 4 hours for the paint to dry, then apply 2nd coat over. You could dry it faster by switching on the fan and open up the windows.
How much does it cost to paint 4 room HDB flats?
To engage us (professional painters) to paint a 4 room HDB, the rough estimate cost is $1,350. We are using Nippon Vilinax (up to 3 colours) for the wall, and using Nippon Matex (white only) for the ceiling.
For other types of Nippon paint, do check with us.
How many hours between painting walls?
It takes about 2 to 4 hours for the paint to dry in Singapore.
How long it takes to paint a 4 room HDB with 1 person?
It will take about 4 to 5 days to paint a 4 room HDB with only 1 person.